Article 10For: Plant manager24 Nov 20269 min read

Operator efficiency in Odoo: set-up time and output per worker

Odoo Community records who started a work order, a planned set-up time and the real duration. Its timer has no set-up state and no quantity per worker. What one manufacturer with 500+ people records.

In short. Operator efficiency needs three records for each worker: the time, the quantity and the standard. Odoo Community records the user who started each work order, the real duration and a planned set-up time. Its timer does not split set-up from run time, and it stores no quantity for each worker. In Case 01, a manufacturer with more than 500 people records a timer and a quantity for each worker. Its timer has no set-up state yet.

Plant managers ask this question to compare crews, to find training needs and to check standard times. This article shows the records of standard Odoo Community, the records that Case 01 added, and the gaps.

How do you calculate operator efficiency?

Divide the real output of the worker by the output that the standard expects.

Measure Formula Records that the ERP must hold
Productivity Good pieces ÷ hours of run time A quantity and a timer for each worker
Efficiency Productivity ÷ standard rate × 100 The same records, and a standard rate for each operation
Set-up time Minutes from the last piece of one run to the first good piece of the next run The start and the end of each set-up, and the worker

The definition of set-up time comes from the Lean Enterprise Institute.

What does Odoo Community record for each worker?

Odoo Community records the user, the start, the end and the duration of each work period. It does not record the employee or the quantity of each person, and its timer has no set-up state. We read the Community source code of the Odoo version that Case 01 runs, on 24 November 2026.

Record Odoo Community Case 01 (on Community)
Who did the work The user who pressed Start The employee on each time log
Start, end and duration One time log for each Start and Pause One timer for each worker. Shared time counts once
Planned set-up time Setup Time and Cleanup Time for each work centre, and for each product in Product Capacities A set-up time for each BoM operation
Real set-up time Not on the timer. Only as a block of the work centre, with the loss reason Setup and Adjustments Not on the timer
Expected against real time Expected Duration, Real Duration, Duration Per Unit and Duration Deviation (%) on each work order A list with the expected beside the real duration, with Excel export
Quantity for each worker One produced quantity for each work order The quantity that each person registers in each shift
OEE and loss categories For each work centre, for the last month. The report can group the time by user Not used yet
Efficiency of each worker against a standard Not found Not built

The Odoo documentation shows one more record in Odoo Enterprise. It is the time of each operator on each work order, with a PIN on the Shop Floor screen.

Odoo also calculates Performance for each work centre. This is the expected duration of the work orders finished in the last month, divided by their real duration. That is the efficiency formula, but for a machine and not for a person. For OEE and loss reasons, read the article about lean manufacturing.

Can Odoo measure the set-up time of each worker?

In part. The timer of a work order does not split set-up from run time. There, set-up time is a planned number. Each work centre has a Setup Time and a Cleanup Time, in minutes. Odoo adds them to the expected duration of each work order:

expected duration = set-up + clean-up + cycles × cycle time × 100 ÷ time efficiency

The real duration is one total for the set-up and the run time.

There are three ways to measure the real set-up time.

  • With a block. On the card of the work centre, block it with the standard loss reason "Setup and Adjustments". Unblock it when the set-up is complete. The time log holds the user, the start, the end and the duration. OEE counts this time as an availability loss. The log names no work order. The block also stops the open timers of the work orders on that work centre. We did a test of the block and the time log on a test database of Odoo Community on 24 November 2026.
  • With one more operation. Make the set-up its own operation in the BoM. It becomes one more work order, with its own time logs.
  • With a small module. Give the timer two states: set-up and run. One tap starts the set-up, and one tap starts the run.

What can a report for each worker look like?

The table below is an example. All its numbers are made up. Case 01 does not have this report.

Worker or crew Work orders Set-up, planned (min) Set-up, real (min) Run time (h) Good pieces Pieces per hour Standard rate Efficiency
Worker A 6 120 138 31.0 46,500 1,500 1,600 94%
Worker B 5 100 92 28.5 39,900 1,400 1,600 88%
Crew C (3 people) 7 210 245 36.0 61,200 1,700 1,600 106%

Compare only the same machine and the same product family. A short run makes each set-up look large.

How does Case 01 record who did which work?

Case 01 is a Vietnamese packaging manufacturer with more than 500 people in two plants. It runs Odoo Community with modules that Hoply.Works wrote. The functions below are general: they do not depend on packaging. Workers use a Shop Floor screen on phones. Read the article about the shop floor on phones.

  1. Sign in on the phone. Each worker signs in on the Shop Floor screen. A crew can sign in on one phone.
  2. Start a timer for each person. Each worker has one timer on a work order. Pause stops the timer of that worker only.
  3. Register the quantity for each shift. Each person registers the quantity that they made in their shift. The record holds the person, the quantity, the time and the work order. The quantity of the order is the sum of these records.
  4. Plan the set-up time for each operation. Each BoM operation can have its own set-up time. If it has none, the ERP uses the Setup Time of the work centre.
  5. Read one page for each worker. A manager selects a worker and two dates. The page shows the orders, the pieces registered, the labels printed, the late registrations and the items to check. A time line shows each work order that the worker started. A second table shows the totals for all workers. The page changes no data.
  6. Show the worker their own record. A tab shows each worker their own registrations of the last 31 days. On a finished work order, the worker can send one request to correct the quantity, with a reason.

Two rules protect the data. A timer that is open for more than 12 hours shows as "Check" on the machine board. Steps that nobody registered close themselves after 24 hours. The page then counts a late registration for each person of that crew.

The timer has 18 automated tests, the page for each worker has 10, and the registration deadline has 25. The timer is not the attendance record. For the hours at the gate, read the article about overtime rules.

What Case 01 does not do yet

  • Real set-up time. The timer has no set-up state. On a work order, the set-up time is a planned number only.
  • Pieces per hour for each worker. The ERP holds the time and the quantity of each worker. No report divides one by the other yet.
  • Efficiency against the standard. Each operation has a standard cycle time. No report compares a worker or a crew with it.
  • A split of the quantity inside a crew. The quantity goes to the person who registers it. For shared work, only a crew measure is correct.
  • Time that nobody tapped. A work order that nobody timed gets its expected duration, not a real duration.

We can add the first three items as modules on the records above.

When does this not fit?

  • The machine sets the speed. On an automatic line, the worker does not control the rate. Measure the machine.
  • The work is crew work. When a crew runs one line, a number for each person is not correct. Measure the crew.
  • Workers do not tap. The numbers are only as good as the Start and Pause taps. Make the taps correct first.
  • The purpose is not agreed. A measure for each person can harm trust. Workers then change the taps, not the work. Agree the purpose with the crews first.
  • The workers do not know about the record. A record for each worker is personal data. Tell the workers what the ERP records, and who reads it. Check the personal data rules that apply to your company.

What to send us

  1. How you record the worker, the time and the quantity today: paper, a spreadsheet or a system.
  2. Your standard times for one machine: the set-up minutes and the standard rate.
  3. The number of work centres, and where people work alone or in crews.

Read next: Lean manufacturing on Odoo Community: what the ERP does, and what it does not do · Case 01: people on the floor · Talk to us

Sources